What net metering means

Net metering connects your rooftop solar system to the grid in both directions. During the day, when your panels produce more than your home is using, the surplus flows out to the grid. At night, or on cloudy days, you draw power from the grid as usual.

A bi-directional (net) meter records both flows: units imported from the grid and units exported to it.

How your bill is calculated

At the end of each billing cycle, the DISCOM bills you on the net figure: units imported minus units exported.

  • If you imported 300 units and exported 220, you pay for 80 units, plus fixed charges.
  • If you exported more than you imported, the extra units are usually carried forward as a credit to the next bill.

Fixed and demand charges do not go away with solar, which is why a bill rarely reaches exactly zero.

What happens to surplus units

Credits that are still unused at the end of the settlement period, usually the financial year, are settled according to your state regulator's rules. In most states they are paid at a feed-in rate set by the regulator, which is much lower than the retail tariff you pay.

This is why it pays to size the system to your own consumption rather than to the whole roof.

Net metering vs gross metering

  • Net metering: solar power first runs your home; only the surplus is exported. Your saving is at your retail tariff, which is usually the better deal for a household.
  • Gross metering: all solar generation is exported and paid at a fixed rate, while you pay for all your consumption separately.

PM Surya Ghar systems for individual households are normally connected under net metering.

How to apply

  1. Apply for rooftop solar on the PM Surya Ghar portal or your DISCOM's portal. The net metering request is part of the same process.
  2. The DISCOM checks technical feasibility, including the capacity of the local transformer.
  3. After installation, the DISCOM tests and installs the net meter and inspects the system.
  4. Your next bills show imported units, exported units and the net figure.

Net metering in Bihar

In Bihar, rooftop net metering is governed by the Bihar Electricity Regulatory Commission's 2018 Net and Gross Metering Regulations and handled by NBPDCL in north Bihar and SBPDCL in south Bihar.

In July 2026 the commission waived the application fee and meter testing charges for domestic consumers installing rooftop solar under PM Surya Ghar with net metering. In October 2026 it published a draft amendment that proposes a 1 kWp minimum, a cap of 500 kWp or the sanctioned load, and paying unused year-end surplus at 50 percent of the approved feed-in tariff. That draft was open for comments and was not final at the time of writing.

Before you sign

  • Ask your installer who files the net metering application and who pays any meter cost.
  • Check that your sanctioned load is at least the size of the solar system, or apply to increase it.
  • Read your first two bills after commissioning to make sure exported units are being credited.

Sources

Rules differ by state and change often. Confirm with your DISCOM and state regulator.